I submitted on Monday my last graded Report, which dealt about a construction project.
To: John
Redforest (CEO of Leatty)
From: Lennard Weiss (Representative of Leatty)
Date: 12 December 2011
Subject: Suggestions for a strategy to rescue the
Shanghai construction project
Introduction
On 12 December, Joep Breurkens and Pascal Corée (Managers of Shanghai Works), Rick van der Werf and
Lennard Weiss (Representatives of Leatty) held a meeting developing a strategy to
rescue the Shanghai construction project. We need to develop a new strategy in
order to push the construction progress catching up the time that was lost due
to delays in previous working sections. We have agreed on the following plan of
action to overcome our project problems and to avoid complications in upcoming
future projects.
Improving information
exchange and co-ordination of tasks
Firstly, we advise establishing an online bulletin
board providing all project parties with the opportunity to exchange
information and to co-ordinate their tasks.
Furthermore, we propose to show the work process in
flow and Gantt charts illustrating the project life cycle in phases and
sub-phases. All this will avoid co-ordination problems of tasks, which arose in
the past. The responsibility lies with the IT Manager of Leatty.
Creating open team communication
channels
Secondly, we have agreed on introducing daily
gatherings directed by the construction managers with the whole working team on
the building site to achieve better team communication. This will help
preventing miscommunication on the spot and create a coordinated workflow. The
responsibility lies with the project manager of Shanghai Works.
Achieving a good working
morale and motivation
Thirdly, we recommend hiring more construction workers
to take the pressure off the whole construction team. Moreover, we advise
introducing an intrinsic and extrinsic reward system creating inducements to
work goal-oriented to regain the morale and motivation of the construction
workers. The responsibility lies with the project coordinator of Shanghai Works.
Suggestions to be
considered in future
Finally, backup plans should be prepared for future
projects in case subcontractors are not able to perform or deliver their goods
or tasks, thus causing delays in our present project. Furthermore, a good communication
with the local government would be considerable as we had problems with
incoming goods due to road works, which could easily have been prevented.
Conclusion and
recommendation
The consulting team realizes that implementing these
recommendations will be necessary to regain our time schedule. Moreover we
firmly believe that we can regain a good team communication as well as a good
working morale and motivation through intrinsic and extrinsic reward systems.
We look forward to your reaction and we hope that
these proposals will comply with your requirements.
Lennard Weiß
(Representative of Leatty)
Evaluating now my report with http://conc.lextutor.ca/vp/eng/output.pl?action=#editor
I can illustrate the use of the different kind of words.
This illustrates that I used a lot more AWL Words (16,55%) compared to my last graded Report.
This could be, because I focused a lot on using words from the Business Briefs that are given via NESTOR.